EVM Calculator

Use this EVM calculator to separate cost risk from schedule risk before project recovery decisions are made.

Planning estimate

Live calculator

EVM calculator

StatusCost and schedule risk

-$40,000 cost variance and -$40,000 schedule variance.

CPI0.91

Earned value divided by actual cost.

SPI0.91

Earned value divided by planned value.

Earned value summary

Keep EV, PV, AC, and BAC on the same scope, progress rule, currency, and reporting date.

EVM measureValue
Earned value$420,000
Planned value$460,000
Actual cost$460,000
Cost variance-$40,000
Schedule variance-$40,000
Cost performance index0.91
Schedule performance index0.91
Estimate at completion$985,714
Estimate to complete$525,714
Variance at completion-$85,714
Planning note

EVM is only as reliable as the progress rule and reporting boundary. Use it with schedule risk, scope changes, quality signals, and delivery context before changing commitments.

Planning comparison only. Check estimates, omitted costs, timing, and constraints before making an operating decision.

Formula

EVM formula

CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPI

Use one scope baseline, progress rule, currency, and reporting date before comparing EV, PV, AC, and BAC.

How to use

Steps

  1. Enter earned value for completed work under the project progress rule.
  2. Enter planned value and actual cost for the same scope and reporting date.
  3. Add budget at completion if you want EAC, ETC, and VAC planning outputs.
  4. Read CPI and SPI together before deciding whether the issue is cost, schedule, or both.

Example

Sample calculation

Earned value$420,000
Planned value$460,000
Actual cost$460,000
StatusCost and schedule risk

Calculator use

Best for

  • Pricing, runway, cash flow, or work assumptions before an operating decision.
  • Base, conservative, and optimistic cases with visible inputs.

Before relying on it

Check first

  • Use one scope baseline, progress rule, currency, and reporting date before comparing EV, PV, AC, and BAC.
  • Mixing scenarios, units, or time periods in one comparison.
  • Leaving out material costs, capacity limits, uncertainty, or dependencies.

Details

What to know before using the result

Cost signalCV and CPI

Negative CV and CPI below 1.00 indicate the project is earning less value per dollar spent.

Schedule signalSV and SPI

Negative SV and SPI below 1.00 indicate earned progress is behind the planned value baseline.

Forecast boundaryEAC from current CPI

The EAC estimate assumes current cost performance continues; update it when recovery plans or scope change.

Benchmarks

How to read the result

Cost variance: EV - AC.

Positive is favorable; negative means actual cost is higher than earned value.

Schedule variance: EV - PV.

Positive is favorable; negative means earned progress is behind planned value.

Performance indexes: CPI = EV / AC; SPI = EV / PV.

Values above 1.00 are favorable; values below 1.00 indicate cost or schedule pressure.

Calculator accuracy

Methodology and assumptions

Formula, inputs, limitations and review record
Formula

CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPI

Inputs used

Earned value, Planned value, Actual cost, Budget at completion

Limitations

Business results depend on contracts, accounting treatment, taxes, payment timing, refunds, collections, and operating assumptions.

Review record

Catalog QA baseline on June 6, 2026. This date marks the catalog-wide automated and editorial QA baseline, not a tool-specific expert review.

Cite this page

Toolkit Shelf. EVM Calculator. https://toolkitshelf.com/tools/evm-calculator

FAQ

Common questions

What is the difference between CPI and SPI?

CPI compares earned value with actual cost. SPI compares earned value with planned value. One can look healthy while the other is at risk.

When does EVM become misleading?

EVM becomes misleading when EV, PV, AC, and BAC are not tied to the same scope, progress rule, reporting date, and currency.

Does EVM replace a project forecast?

No. It is an early warning system. Use it with updated scope, schedule risk, quality risk, and recovery assumptions before making commitments.