Formula
EVM formula
CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPIUse one scope baseline, progress rule, currency, and reporting date before comparing EV, PV, AC, and BAC.
Use this EVM calculator to separate cost risk from schedule risk before project recovery decisions are made.
Live calculator
-$40,000 cost variance and -$40,000 schedule variance.
Earned value divided by actual cost.
Earned value divided by planned value.
Keep EV, PV, AC, and BAC on the same scope, progress rule, currency, and reporting date.
| EVM measure | Value |
|---|---|
| Earned value | $420,000 |
| Planned value | $460,000 |
| Actual cost | $460,000 |
| Cost variance | -$40,000 |
| Schedule variance | -$40,000 |
| Cost performance index | 0.91 |
| Schedule performance index | 0.91 |
| Estimate at completion | $985,714 |
| Estimate to complete | $525,714 |
| Variance at completion | -$85,714 |
EVM is only as reliable as the progress rule and reporting boundary. Use it with schedule risk, scope changes, quality signals, and delivery context before changing commitments.
Planning comparison only. Check estimates, omitted costs, timing, and constraints before making an operating decision.
Formula
CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPIUse one scope baseline, progress rule, currency, and reporting date before comparing EV, PV, AC, and BAC.
How to use
Example
Calculator use
Before relying on it
Details
Negative CV and CPI below 1.00 indicate the project is earning less value per dollar spent.
Negative SV and SPI below 1.00 indicate earned progress is behind the planned value baseline.
The EAC estimate assumes current cost performance continues; update it when recovery plans or scope change.
Source notes
Benchmarks
Positive is favorable; negative means actual cost is higher than earned value.
Positive is favorable; negative means earned progress is behind planned value.
Values above 1.00 are favorable; values below 1.00 indicate cost or schedule pressure.
Calculator accuracy
CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV; EAC = BAC / CPI
Earned value, Planned value, Actual cost, Budget at completion
Business results depend on contracts, accounting treatment, taxes, payment timing, refunds, collections, and operating assumptions.
Catalog QA baseline on June 6, 2026. This date marks the catalog-wide automated and editorial QA baseline, not a tool-specific expert review.
Toolkit Shelf. EVM Calculator. https://toolkitshelf.com/tools/evm-calculator
FAQ
CPI compares earned value with actual cost. SPI compares earned value with planned value. One can look healthy while the other is at risk.
EVM becomes misleading when EV, PV, AC, and BAC are not tied to the same scope, progress rule, reporting date, and currency.
No. It is an early warning system. Use it with updated scope, schedule risk, quality risk, and recovery assumptions before making commitments.
Leave passwords, account numbers, and private medical or tax information out of your report.